Bayliss Boatworks construction update: Blue View - Bayliss 78'

by John Bayliss 3 May 2020 11:08 UTC

Our crews have been hitting big milestones on Blue View! We are seeing finalizations daily as we inch closer to her delivery later this month.

Padded panels are installed throughout the entire lower level. The beautiful olive ash burl headboards within the VIP and master staterooms provide focal points amongst the surrounding teak cabinetry.

In late April, carpet was laid throughout the lower level spaces and Tempur-Pedic mattresses were placed in each bunk. Gas shocks have been installed on the pullman bunks, allowing them to lower and raise at the touch of a button.

Our metalworks department has installed our proprietary custom television-lifts within the salon and dinette. These lifts have been engineered for stability and are capable of remaining raised while running the boat, even in rough conditions. To finalize the galley cabinetry, we are fabricating and installing customized nesting spaces for each pot, pan, and kitchen appliance.

At the end of April, the sofas were installed in the master stateroom and salon. Our interior carpentry crew will now gas shock each one for easy access to the storage spaces below. The salon carpeting and teak entryway floor are next up for installations.

Within each head, teak vanities, toilet pedestals, and sleek stainless steel fixtures are in place. Tackle room installations are nearly complete. Our crew has created custom nesting spaces to showcase and easily access each rod, reel, and LP.

Blue View will be christened later this month and we can't wait to release her to the world!

Read more about Blue View here...

Related Articles

Bayliss Boatworks new construction updates
Big news from Big Deal! Big news from Big Deal! Late last month, she successfully completed her first sea trial—a major milestone as she moves closer to delivery. Posted on 2 May
Bayliss Boatworks new construction updates
Big Deal is reaching significant milestones Big Deal is reaching significant milestones, starting with a major exterior update. Posted on 2 Apr
Bayliss Boatworks new construction updates
Big Deal was moved to the paint facility early last month to begin the full paint process Following our paint team's meticulous sanding of the hull, Big Deal was moved to our paint facility early last month to begin the full paint process. Posted on 2 Mar
Bayliss Boatworks new construction updates
Big Deal ready for its scheduled move to the paint bay in early March With the bridge console faired, our paint team is steadily progressing with priming and sanding, getting Big Deal ready for its scheduled move to the paint bay in early March. Posted on 1 Feb
Bayliss Boatworks new construction updates
Progress on Big Deal continues as the cockpit and mezzanine have been outfitted Progress on Big Deal continues as the cockpit and mezzanine, now fully primed, have been outfitted with a teak bullnose, teak decking, and teak mezzanine lids by our exterior carpentry team. Posted on 2 Jan
Bayliss Boatworks new construction updates
The paint team has started applying primer to the mezzanine on Big Deal With the mezzanine buildout complete on Big Deal, the paint team has started applying primer to the area. Posted on 3 Dec 2024
Max Bet Bayliss 64' on the water
The culmination of over 60,000 man-hours of dedicated craftsmanship The well-respected team behind Max Bet is no stranger to the Bayliss Boatworks family, having previously entrusted us with the repower of their 66' Spencer. Posted on 4 Nov 2024
Bayliss Boatworks new construction updates
Big Deal Bayliss 75', Tarheel Bayliss 64', Mama Seata Bayliss 76' With the glassing phase complete on Big Deal's mezzanine, our exterior team has applied Awlfair, and sanding is currently under way to ensure a smooth, polished finish before the primer is applied. Posted on 3 Nov 2024
Bayliss Boatworks new construction updates
Max Bet will reside dockside until her christening later this month Max Bet will reside dockside until her christening later this month, with our mechanical team testing and proving all systems. Posted on 1 Oct 2024
Bayliss Boatworks new construction updates
DekIt team joined us this month to install nonskid foam decking in the engine room After a successful first sea trial earlier this month, our interior carpentry team jumped back onto Max Bet to assist with the installation of granite countertops in the lower staterooms. Posted on 2 Sep 2024