Bayliss Boatworks new construction updates

by Bayliss Boatworks 2 Apr 17:31 UTC
 
Big Deal is reaching significant milestones, starting with a major exterior update: Palm Beach Towers has successfully installed the tower and hardtop, marking a pivotal step in the construction process.

Inside, our interior carpentry team is pulling together every detail. Cabinetry is now in place in both the pantry and dayhead, while the companionway has been enhanced with a refined teak staircase complete with a matching border.  In the master stateroom, our team installed a custom teak-veneered bunk with gas-spring-assisted lifting, making it easy to access the storage area below.
CLICK TO READ MORE ABOUT BIG DEAL
 
Our exterior carpentry team is making steady headway on Tarheel, focusing on the mezzanine and bridge console buildouts. The bridge console is now taking shape, while on the mezzanine, boxes have been sprayed with primer, and stainless steel liners have been fabricated in preparation for refrigeration coil installation.

Inside, our electrical crew has installed the salon transformers and wired the MSR air handler. Each one of these steps builds toward the completion of a milestone in the construction process, and we are excited to see the next step in Tarheel's journey!
CLICK TO READ MORE ABOUT TARHEEL
 
Mama Seata had another big month! After sanding and priming in the engine room, pump room, and beneath the salon deck, our skilled paint team applied top coat in preparation for installing the engines and generators. The mechanical team, in collaboration with Hathaway Marine, then successfully installed her generators, engines, and salon/pump room decking.

Following these milestones, Mama Seata was moved to the main shop, where she will remain until her cabin installation in the coming months.
CLICK TO READ MORE ABOUT MAMA SEATA
 
Following the whiskey plank on Crisdel, the sheer guard was installed, and our hull carpentry team promptly began sanding the hull sides and bottom in preparation for glassing. Scaffolding was built to provide easy access for working on the bottom and sides.

Recently, the engine vents were glassed in place, and glassing of the hull bottom was completed. After sanding, the hull bottom was coated with Awlfair, and sanding continued. Up next, the hull carpentry team will apply SuperBuild to the hull bottom before beginning the glassing process on the hull sides.
CLICK TO READ MORE ABOUT BAYLISS 64'
 
 
 
Website
Website
Facebook
Facebook
Instagram
Instagram
Copyright © 2025 Bayliss Boatworks All rights reserved.
www.baylissboatworks.com 
 

Related Articles

Bayliss Boatworks new construction updates
Big Deal was moved to the paint facility early last month to begin the full paint process Following our paint team's meticulous sanding of the hull, Big Deal was moved to our paint facility early last month to begin the full paint process. Posted on 2 Mar
Bayliss Boatworks new construction updates
Big Deal ready for its scheduled move to the paint bay in early March With the bridge console faired, our paint team is steadily progressing with priming and sanding, getting Big Deal ready for its scheduled move to the paint bay in early March. Posted on 1 Feb
Bayliss Boatworks new construction updates
Progress on Big Deal continues as the cockpit and mezzanine have been outfitted Progress on Big Deal continues as the cockpit and mezzanine, now fully primed, have been outfitted with a teak bullnose, teak decking, and teak mezzanine lids by our exterior carpentry team. Posted on 2 Jan
Bayliss Boatworks new construction updates
The paint team has started applying primer to the mezzanine on Big Deal With the mezzanine buildout complete on Big Deal, the paint team has started applying primer to the area. Posted on 3 Dec 2024
Max Bet Bayliss 64' on the water
The culmination of over 60,000 man-hours of dedicated craftsmanship The well-respected team behind Max Bet is no stranger to the Bayliss Boatworks family, having previously entrusted us with the repower of their 66' Spencer. Posted on 4 Nov 2024
Bayliss Boatworks new construction updates
Big Deal Bayliss 75', Tarheel Bayliss 64', Mama Seata Bayliss 76' With the glassing phase complete on Big Deal's mezzanine, our exterior team has applied Awlfair, and sanding is currently under way to ensure a smooth, polished finish before the primer is applied. Posted on 3 Nov 2024
Bayliss Boatworks new construction updates
Max Bet will reside dockside until her christening later this month Max Bet will reside dockside until her christening later this month, with our mechanical team testing and proving all systems. Posted on 1 Oct 2024
Bayliss Boatworks new construction updates
DekIt team joined us this month to install nonskid foam decking in the engine room After a successful first sea trial earlier this month, our interior carpentry team jumped back onto Max Bet to assist with the installation of granite countertops in the lower staterooms. Posted on 2 Sep 2024
Bayliss Boatworks new construction updates
Max Bet 64', Big Deal Bayliss 75', Tarheel Bayliss 64' We are gearing up for Max Bet's first splash! Our mechanical and electrical teams have been busy installing the washer/dryer, sonar, and heat exchanger components, while Custom Marine Electronics has been working in the bridge. Posted on 3 Aug 2024
Bayliss Boatworks new construction updates
Max Bet 64', Big Deal Bayliss 75', Tarheel Bayliss 64' Next up for completion, Max Bet is drawing closer to the project's finish line! Our electrical team has been busy wiring the hardtop and the main panel. Posted on 5 Jul 2024