Bayliss Boatworks new construction updates

by Bayliss Boatworks 1 Feb 22:59 UTC
 
With the bridge console faired, our paint team is steadily progressing with priming and sanding, getting Big Deal ready for its scheduled move to the paint bay in early March. Everett Nautical has returned to apply faux teak to the transom and bridge cap, enhancing the vessels sleek, timeless aesthetic.

Inside, the interior carpentry crew has been busy installing veneers in the salon and assembling various cabinetry pieces in the lower accommodations, including the bunk in the Master Stateroom.
CLICK TO READ MORE ABOUT BIG DEAL
 
The bridge buildout on Tarheel is progressing smoothly, with fabrication of the port and starboard seating well underway. In the cockpit, the exterior carpentry team has been glassing the bridge wings and washboards, ensuring both structural integrity and a flawless finish.

Meanwhile, our mechanical and electrical teams have made significant strides, installing the galley sink plumbing, salon drain manifolds, forward fuel tank plumbing, and bilge/sump discharges. In the salon, MTU bridge and tower cables have been run, along with the generator and wire connections to the main panel, ensuring all systems are integrated and ready for the next stages of construction.
CLICK TO READ MORE ABOUT TARHEEL
 
In early January, Mama Seata was moved outdoors for the installation of her forward fuel tank. Once the tank was securely placed, the hull carpentry team resumed work, installing structural decking over the tank to form a solid base for the machine tunnel decking.
In the engine room, the battery boxes and generator shelves have been glassed in place. With Awlfair now applied, our paint crew has begun sanding in preparation for the next finishing stage.
CLICK TO READ MORE ABOUT MAMA SEATA
 
The planking process on Bayliss 64s hull bottom is complete! With this phase finished, our hull carpentry team is shifting focus to the hull sides.

To prepare for this next step, long, flexible wooden battens are being cut and installed. These battens help shape the hull and ensure precise plank alignment, creating the smooth, flowing lines that define Bayliss craftsmanship.

Looking ahead: once the final hull plank is installed, our team will mark the occasion with the traditional whiskey plank celebration!
CLICK TO READ MORE ABOUT BAYLISS 64'
 
 
 
Website
Website
Facebook
Facebook
Instagram
Instagram

Copyright © 2025 Bayliss Boatworks All rights reserved.
www.baylissboatworks.com 

 

Related Articles

Bayliss Boatworks new construction updates
Progress on Big Deal continues as the cockpit and mezzanine have been outfitted Progress on Big Deal continues as the cockpit and mezzanine, now fully primed, have been outfitted with a teak bullnose, teak decking, and teak mezzanine lids by our exterior carpentry team. Posted on 2 Jan
Bayliss Boatworks new construction updates
The paint team has started applying primer to the mezzanine on Big Deal With the mezzanine buildout complete on Big Deal, the paint team has started applying primer to the area. Posted on 3 Dec 2024
Max Bet Bayliss 64' on the water
The culmination of over 60,000 man-hours of dedicated craftsmanship The well-respected team behind Max Bet is no stranger to the Bayliss Boatworks family, having previously entrusted us with the repower of their 66' Spencer. Posted on 4 Nov 2024
Bayliss Boatworks new construction updates
Big Deal Bayliss 75', Tarheel Bayliss 64', Mama Seata Bayliss 76' With the glassing phase complete on Big Deal's mezzanine, our exterior team has applied Awlfair, and sanding is currently under way to ensure a smooth, polished finish before the primer is applied. Posted on 3 Nov 2024
Bayliss Boatworks new construction updates
Max Bet will reside dockside until her christening later this month Max Bet will reside dockside until her christening later this month, with our mechanical team testing and proving all systems. Posted on 1 Oct 2024
Bayliss Boatworks new construction updates
DekIt team joined us this month to install nonskid foam decking in the engine room After a successful first sea trial earlier this month, our interior carpentry team jumped back onto Max Bet to assist with the installation of granite countertops in the lower staterooms. Posted on 2 Sep 2024
Bayliss Boatworks new construction updates
Max Bet 64', Big Deal Bayliss 75', Tarheel Bayliss 64' We are gearing up for Max Bet's first splash! Our mechanical and electrical teams have been busy installing the washer/dryer, sonar, and heat exchanger components, while Custom Marine Electronics has been working in the bridge. Posted on 3 Aug 2024
Bayliss Boatworks new construction updates
Max Bet 64', Big Deal Bayliss 75', Tarheel Bayliss 64' Next up for completion, Max Bet is drawing closer to the project's finish line! Our electrical team has been busy wiring the hardtop and the main panel. Posted on 5 Jul 2024
Bayliss Boatworks Sequentis Bayliss 60' update
The idea of the new project was a first for the company As a custom sportfishing boatbuilder, we take the requests of our owners and do our best to bring them to life. When collaborating with a long-time Bayliss Boatworks customer, the vision for a 60' walkaround was put on the drawing board. Posted on 4 Jul 2024
Bayliss Boatworks new construction updates
The final touches are wrapping up on our first walkaround build! The final touches are wrapping up on our first walkaround build! Posted on 2 Jun 2024