Bayliss Boatworks new construction updates: Big Deal 75', Tarheel 64', Mama Seata 76'

by Bayliss Boatworks 3 Nov 20:00 UTC
Big Deal - Bayliss 75' © Bayliss Boatworks

Big Deal (Bayliss 75')

With the glassing phase complete on Big Deal's mezzanine, our exterior team has applied Awlfair, and sanding is currently under way to ensure a smooth, polished finish before the primer is applied.

On the bridge, the console buildout is in progress, with the forward freezer storage boxes starting to take shape beneath the console seating area.

Down below, our mechanical crew has finalized the plumbing for the bow thruster, while work on the black water plumbing continues in the machine tunnel. In the lower accommodations, our interior team is busy fabricating custom cabinetry items to enhance aesthetics and functionality in the staterooms and heads.

We're always excited to welcome the talented team from Everett Nautical back to the shop. They visited last month to apply faux teak to the toe rail and half round.

Read more about the Big Deal

Tarheel Bayliss 64'

The bow deck on Tarheel is now in finish primer! Our paint team has shifted aft and is currently spraying primer on the bridge overhang.

In the cockpit, our exterior department has installed the structural decking, laying the groundwork for the teak deck that will be added later in the build process.

Meanwhile, our interior team has been hard at work installing mockups in the lower accommodations, allowing each room to truly take shape.

Read more about the Tarheel

Mama Seata Bayliss 76'

With Mama Seata's hull upright, our hull carpentry team wasted no time adding hullside insulation and installing the interior bulkheads. The interior bulkheads clearly define the spaces for the pump room and engine room.

Up forward, the buildout of the machine tunnel has begun! This essential component will house the mechanical systems, including spare parts, and facilitate access for maintenance. On the exterior, the lifting strakes and bow thruster tube have now been successfully installed.

In the coming weeks, our hull carpentry team will add the bow thruster fairing and begin fabricating battery boxes for the engine room.

Read more about the Mama Seata

Related Articles

Max Bet Bayliss 64' on the water
The culmination of over 60,000 man-hours of dedicated craftsmanship The well-respected team behind Max Bet is no stranger to the Bayliss Boatworks family, having previously entrusted us with the repower of their 66' Spencer. Posted on 4 Nov
Bayliss Boatworks new construction updates
Max Bet will reside dockside until her christening later this month Max Bet will reside dockside until her christening later this month, with our mechanical team testing and proving all systems. Posted on 1 Oct
Bayliss Boatworks new construction updates
DekIt team joined us this month to install nonskid foam decking in the engine room After a successful first sea trial earlier this month, our interior carpentry team jumped back onto Max Bet to assist with the installation of granite countertops in the lower staterooms. Posted on 2 Sep
Bayliss Boatworks new construction updates
Max Bet 64', Big Deal Bayliss 75', Tarheel Bayliss 64' We are gearing up for Max Bet's first splash! Our mechanical and electrical teams have been busy installing the washer/dryer, sonar, and heat exchanger components, while Custom Marine Electronics has been working in the bridge. Posted on 3 Aug
Bayliss Boatworks new construction updates
Max Bet 64', Big Deal Bayliss 75', Tarheel Bayliss 64' Next up for completion, Max Bet is drawing closer to the project's finish line! Our electrical team has been busy wiring the hardtop and the main panel. Posted on 5 Jul
Bayliss Boatworks Sequentis Bayliss 60' update
The idea of the new project was a first for the company As a custom sportfishing boatbuilder, we take the requests of our owners and do our best to bring them to life. When collaborating with a long-time Bayliss Boatworks customer, the vision for a 60' walkaround was put on the drawing board. Posted on 4 Jul
Bayliss Boatworks new construction updates
The final touches are wrapping up on our first walkaround build! The final touches are wrapping up on our first walkaround build! Posted on 2 Jun
Bayliss Boatworks new construction updates
The latest 75' build at Bayliss Boatworks: Big Deal We are excited to debut the name of the latest 75' build at Bayliss Boatworks: Big Deal. Posted on 3 May
Bayliss Boatworks new construction updates
Sequentis is getting closer to hitting the water! Earlier in March, our mechanical team with the help of Palm Beach Towers installed her custom hardtop. Posted on 2 Apr
Bayliss Boatworks new construction updates
Our first walkaround build is really coming together! Our first walkaround build is really coming together! With full paint complete, Sequentis returned to the main shop's make-ready bay for our exterior carpentry team to prep for tower installation. Posted on 2 Mar