Bayliss Boatworks construction update: Bayliss 75'

by Bayliss Boatworks 6 Jul 2021 19:25 UTC
Bayliss 75' © Bayliss Boatworks

Progress continued this past month on Bayliss 75'. The Paint Department has been working on sanding the flybridge console and seating area.

Down below, the cockpit structural decking was sanded and glassed, and the fishbox was also installed and glassed. Our Exterior Carpentry Crew has begun construction on the washboards for Hull 27, which will be put in place in the coming weeks.

Our Interior Carpentry Department has been busy installing mockups of cabinets and bunks in the salon, galley and staterooms. The mockups will soon move out of the boat and into the interior carpentry workshop to be fully fabricated, finished and stored before their final install.

Read more about Bayliss 75' here...

Related Articles

Bayliss Boatworks new construction updates
Big Deal ready for its scheduled move to the paint bay in early March With the bridge console faired, our paint team is steadily progressing with priming and sanding, getting Big Deal ready for its scheduled move to the paint bay in early March. Posted on 1 Feb
Bayliss Boatworks new construction updates
Progress on Big Deal continues as the cockpit and mezzanine have been outfitted Progress on Big Deal continues as the cockpit and mezzanine, now fully primed, have been outfitted with a teak bullnose, teak decking, and teak mezzanine lids by our exterior carpentry team. Posted on 2 Jan
Bayliss Boatworks new construction updates
The paint team has started applying primer to the mezzanine on Big Deal With the mezzanine buildout complete on Big Deal, the paint team has started applying primer to the area. Posted on 3 Dec 2024
Max Bet Bayliss 64' on the water
The culmination of over 60,000 man-hours of dedicated craftsmanship The well-respected team behind Max Bet is no stranger to the Bayliss Boatworks family, having previously entrusted us with the repower of their 66' Spencer. Posted on 4 Nov 2024
Bayliss Boatworks new construction updates
Big Deal Bayliss 75', Tarheel Bayliss 64', Mama Seata Bayliss 76' With the glassing phase complete on Big Deal's mezzanine, our exterior team has applied Awlfair, and sanding is currently under way to ensure a smooth, polished finish before the primer is applied. Posted on 3 Nov 2024
Bayliss Boatworks new construction updates
Max Bet will reside dockside until her christening later this month Max Bet will reside dockside until her christening later this month, with our mechanical team testing and proving all systems. Posted on 1 Oct 2024
Bayliss Boatworks new construction updates
DekIt team joined us this month to install nonskid foam decking in the engine room After a successful first sea trial earlier this month, our interior carpentry team jumped back onto Max Bet to assist with the installation of granite countertops in the lower staterooms. Posted on 2 Sep 2024
Bayliss Boatworks new construction updates
Max Bet 64', Big Deal Bayliss 75', Tarheel Bayliss 64' We are gearing up for Max Bet's first splash! Our mechanical and electrical teams have been busy installing the washer/dryer, sonar, and heat exchanger components, while Custom Marine Electronics has been working in the bridge. Posted on 3 Aug 2024
Bayliss Boatworks new construction updates
Max Bet 64', Big Deal Bayliss 75', Tarheel Bayliss 64' Next up for completion, Max Bet is drawing closer to the project's finish line! Our electrical team has been busy wiring the hardtop and the main panel. Posted on 5 Jul 2024
Bayliss Boatworks Sequentis Bayliss 60' update
The idea of the new project was a first for the company As a custom sportfishing boatbuilder, we take the requests of our owners and do our best to bring them to life. When collaborating with a long-time Bayliss Boatworks customer, the vision for a 60' walkaround was put on the drawing board. Posted on 4 Jul 2024