Bayliss Boatworks construction update: Bayliss 67' Overtime

by Bayliss Boatworks 7 Apr 15:19 UTC

Work continues inside the hull of Overtime (Bayliss 67') after being flipped right side up early in the month. Glassing was completed on the interior of the hull bottom before her main structural and engine bulkheads were installed.

With the bottom glassed and bulkheads in place, machine tunnel buildout began and the bow thruster tube installed. Also on the interior, hull side insulation has begun and will progress throughout the rest of the boat in the coming weeks. Buildout was completed for the fresh water tanks and baffles were installed before it moved into glassing.

Overtime's flybridge was wrapped before the entire cabin moved outdoors where it will sit until it's time for installation on the hull.

Read more about Overtime here...

Related Articles

Bayliss 67' Overtime construction update
Forward fuel tank and fuel tank deck installed Overtime (Bayliss 67') had a few installs of her own this past month. The forward fuel tank was installed and the fuel tank deck was installed shortly thereafter. Posted on 7 Jun
Bayliss 72' Old Reliable construction update
She is nearing the final stages of production In the flybridge, our Electrical Department with the help of Custom Marine Electronics installed multiple marine-electronic items. They also installed the electrical panels. Posted on 5 Jun
Bayliss 75' construction update
Our Paint Department has been busy with improvements to the exterior Bayliss 75' peeked out from the construction bay this past month, for the install of her aft fuel tank. The foam insulation was installed shortly after, and we are preparing for the installation of the cockpit decking next. Posted on 3 Jun
Bayliss 67' Overtime construction update
The machine tunnel build-out continues with glassing of the forward fuel tank surround This past month, Overtime (Bayliss 67') had her hull exterior sanded and primed. Down in the engine room, construction of the generator shelves, pump shelf, battery boxes, and bilge is well under way. Posted on 6 May
Bayliss 75' construction update
The exterior carpentry department has been busy glassing the cabin to the hull Advancements to the exterior of Bayliss 75' continued this past month. Now that the cabin and bow deck have been installed, she is ready for lower level paint to begin. Posted on 3 May
Bayliss 72' Old Reliable construction update
The paint department have been hard at work getting ready for the top coat Progress on Old Reliable (Bayliss 72') has been coming along steadily, and she is starting to take shape with her recently installed tower and hardtop. Posted on 2 May
Bayliss 75' construction update
Looking a lot different this month with the addition of her cabin Our mechanical crew also installed her aft gyro, the last of her main mechanical components, before returning back to the construction bay. Posted on 5 Apr
Bayliss 72' Old Reliable construction update
Old Reliable getting more interior and exterior details finalized Old Reliable (Bayliss 72') is on the move from the make-ready bay to the paint bay after a busy month, getting more interior and exterior details finalized. Posted on 3 Apr