Bayliss Boatworks construction update: Bayliss 62' Seven

by Bayliss Boatworks 3 Sep 2020 15:22 UTC

Seven (Bayliss 62') is in the home stretch! In late August, she moved into our paint bay where she received final paint. Our Paint & Fair Crew began their work with the application of a custom-blended shade of Imron "Cool Blue" on Seven's hull.

Next, the bow deck was coated in non-skid paint before the faux teak toe rail and half round received final clear coat. In early September, she'll receive her transom artwork. During her move to the paint bay, the Mechanical Crew took advantage of the outdoor space to install the shafts.

In the cockpit, with the bulkhead in primer and coverboards installed, the Exterior Carpentry Crew began rolling on Seven's remaining cockpit teak work in early August. Installations of teak planking on the cockpit deck and mezzanine were completed just before her move to the paint bay.

As this build nears the finish line, the final mechanical installations will begin to take place. Next up, the Mechanical Crew will plumb the livewell within the lazarette, closely followed by the installation of the icemaker in the engine room companionway.

Within Seven's interior, final teak cabinetry components are filling in piece by piece within the staterooms and heads. While these lower level installations continue, the dinette pedestal, companionway staircase brackets, and a custom television lift for the salon are being fabricated in our Metalworks shop. This month, cabinetry installations will begin in the salon and galley spaces.

The Electrical Crew is in the process of installing and wiring the main panels. The crew will soon begin on the electrical layout and wiring for the flybridge console in preparation for Seven's tower installation which will take place in mid-September.

Read more about Seven here.

Related Articles

Bayliss Boatworks new construction updates
Sequentis is getting closer to hitting the water! Earlier in March, our mechanical team with the help of Palm Beach Towers installed her custom hardtop. Posted on 2 Apr
Bayliss Boatworks new construction updates
Our first walkaround build is really coming together! Our first walkaround build is really coming together! With full paint complete, Sequentis returned to the main shop's make-ready bay for our exterior carpentry team to prep for tower installation. Posted on 2 Mar
Bayliss Boatworks new construction updates
Our teams had a productive month on Sequentis January was a heavy month of boat moves for our mechanical team! After being prepped for final paint, Sequentis was shifted over to our paint facility to have her top coat sprayed. Posted on 3 Feb
Bayliss Boatworks new construction updates
Looking forward to utlizing the new boatyard space in the year ahead The Bayliss Boatyard expansion kicked off this past February, and work is winding down as the project timeline comes to a close. Posted on 2 Jan
Bayliss Boatworks new construction updates
Progress on Sequentis is moving right along! Progress on Sequentis is moving right along! Both the mezzanine buildout and cockpit deck installation are now complete. Posted on 2 Dec 2023
Bayliss Boatworks new construction updates
Steady progress is happening on Sequentis Steady progress is happening on Sequentis. Super Build was applied to the bridge and mezzanine, and crews are now sanding these areas in preparation for primer. Posted on 2 Nov 2023
Bayliss Boatworks new construction updates
Our teams had a productive month on Sequentis Our teams had a productive month on Sequentis. With the teak deck installed on the walkaround, our exterior construction crew is continuing progress on the bridge dash, storage compartments, and mezzanine lids. Posted on 2 Oct 2023
Bayliss Boatworks new construction updates
Hull jig for our latest project: Bayliss 64' assembled This past month, we assembled the hull jig for our latest project: Bayliss 64'. Posted on 2 Sep 2023
Bayliss Boatworks new construction updates
July work on Sequentis 60', Max Bet 64' and Bayliss 75' The mezzanine and bridge buildout on Sequentis kept our exterior carpentry crew busy this past month. Storage and seating can be seen on the bridge now, and fabrication on the forward bridge storage compartments has begun. Posted on 2 Aug 2023
Bayliss Boatworks new construction updates
June was a productive month for our exterior carpentry team June was a productive month for our exterior carpentry team on the walkaround build. Posted on 1 Jul 2023