Bayliss 75' construction update:Lower level cabinetry buildout has quickly progressed
by Bayliss Boatworks 5 May 2018 10:02 UTC
![](/photos/powerboat/yysw201561.jpg)
Primer being applied to cabin © Bayliss Boatworks
Lower level cabinetry buildout has quickly progressed on Bayliss 75' this month. In the Master stateroom, both the bunk and night stands were installed.
Our crew will continue to finish out the Master with continued buildout on the headboard and valence. The flooring in both the VIP and Crew staterooms have been installed, and the VIP cabinetry is in the process of being fabricated.
Our electrical crew is completing the lighting runs, and is also beginning A/V and marine electronics wiring. On the exterior, the toe rail, bow deck, and cabin has been primed. The flybridge console is nearing installation, and the cockpit will begin to receive mezzanine walls and washboards this month!
Read more about Bayliss 75' here