Bayliss Boatworks new construction updates: Sequentis 60', Max Bet 64', Bayliss 75', Bayliss 64'
by Bayliss Boatworks 2 Oct 21:43 UTC

Bayliss 60' Sequentis © Bayliss Boatworks
Bayliss 60' Sequentis
Our teams had a productive month on Sequentis. With the teak deck installed on the walkaround, our exterior construction crew is continuing progress on the bridge dash, storage compartments, and mezzanine lids.
In the lower accommodations, the salon and galley walls have been installed and our interior carpentry team has been busy mocking up cabinetry items. Next on Sequentis, our crew will be installing her cockpit deck.
Read more about Sequentis
Bayliss 64' Max Bet
Forward progress is taking place on Max Bet. Our paint team worked on sanding and applying primer to the hull, bow deck, and cabin sides, while our exterior carpentry crew recently installed the cockpit fishbox and began the mezzanine buildout.
The mechanical crew has been busy in the interior installing ductwork. Over in the cabinet shop, our interior construction crew has fabricated the master and VIP vanity uppers and lowers. We are looking forward to beginning Max Bet's flybridge buildout next.
Read more about Max Bet
Bayliss 75'
Bayliss 75' is now hitting her install milestones. Our hull carpentry team completed the buildout of the fuel tank surround, while our paint team completed painting the area.
The forward fuel tank was installed by our mechanical team, and our hull carpentry team was also able to install the machine tunnel and forward fuel tank decks.
Later this month, Bayliss 75' will have her two MTU 16V 2000M96L engines installed.
Read more about Bayliss 75'
Bayliss 64'
All the pieces are coming together on Bayliss 64'. With the hull jig in place, our hull carpentry team installed the hull stem, then laminated and sanded the sheer log. The stringers were also set in place, and the hull carpentry team has sanded and shaped them. The planking process on Bayliss 64' will begin next!
Read more about Bayliss 64'