Bayliss Boatworks new construction updates: Sequentis 60', Max Bet 64' and Bayliss 75'
by Bayliss Boatworks 2 Jun 2023 17:09 UTC
Sequentis Bayliss 60' © Bayliss Boatworks
Sequentis Bayliss 60'
All the pieces are coming together on the 60' walkaround. Last month on Sequentis, the cockpit structural decking was installed, and epoxy was applied to the interior walls.
Our exterior carpentry crew installed the fishbox and glassed its interior. Currently, our paint team is working on sanding the exterior in preparation for top coat!
Read more about Sequentis...
Bayliss 64' Max Bet
With her cabin in place, our exterior carpentry crew has been busy glassing Max Bet's cabin surround as well as installing the cockpit bulkhead.
In the lower accommodations, the interior walls were glassed in place and Awlfair was applied to the flooring. Our cabinetry team is beginning to tackle the interior mockups, and the mezzanine buildout is under way!
Read more about Max Bet...
Bayliss 75'
Bayliss 75' is right-side up after her recent flip! In May, our hull carpentry crew AdTeched, faired, and sanded the hull bottom before she made the journey to the boatyard where our mechanical team successfully conducted the rollover.
Bayliss 75' was then moved back indoors, and our hull carpentry team began to install insulation and glass the hull's interior. Next month, our crews will work on installing the interior bulkheads.
Read more about Bayliss 75'...