Bayliss Boatworks construction update - Overtime, Sequentis and Max Bet

by Bayliss Boatworks 2 Oct 2022 20:28 UTC
Bayliss 67' Overtime © Bayliss Boatworks

Bayliss 67' Overtime

All the final components are coming together on Overtime! Her transom artwork was completed by Everett Nautical, and our paint department added her bootstripe.

In the salon/galley, our interior carpentry department installed window moldings and in the tackle room the cork wall was put in place. Down in the lower accommodations, wall panels and various cabinetry items have been installed.

Our crews are staying busy finalizing every project detail. Soon, Overtime will make her way to the water where she will stay for the duration of the build.

Read more about the Overtime...

Bayliss 60' Sequentis

Below deck, changes are moving along on Sequentis! With the machine tunnel deck installed, our exterior carpentry crew began working on the salon deck and walk-around support buildout.

The gyro surround walls were also installed, and the aft equipment shelf is currently being glassed. Our paint department has been busy sanding and fairing in the engine room, with priming in the battery boxes now complete. Up next, we are looking forward to priming the engine room!

Read more about Sequentis...

Bayliss 64' Max Bet

Max Bet is officially flipped! In September, our hull carpentry and paint crews glassed, AdTeched, faired, and sanded the hull bottom and installed the engine vents and lower guards.

Ready for rollover, Max Bet made the journey to the boatyard where our mechanical team conducted the flip. Now sitting right side up, she is back at the hull shop awaiting the installation of her bulkheads.

Read more about Max Bet...

Related Articles

Bayliss Boatworks new construction updates
Big Deal ready for its scheduled move to the paint bay in early March With the bridge console faired, our paint team is steadily progressing with priming and sanding, getting Big Deal ready for its scheduled move to the paint bay in early March. Posted on 1 Feb
Bayliss Boatworks new construction updates
Progress on Big Deal continues as the cockpit and mezzanine have been outfitted Progress on Big Deal continues as the cockpit and mezzanine, now fully primed, have been outfitted with a teak bullnose, teak decking, and teak mezzanine lids by our exterior carpentry team. Posted on 2 Jan
Bayliss Boatworks new construction updates
The paint team has started applying primer to the mezzanine on Big Deal With the mezzanine buildout complete on Big Deal, the paint team has started applying primer to the area. Posted on 3 Dec 2024
Max Bet Bayliss 64' on the water
The culmination of over 60,000 man-hours of dedicated craftsmanship The well-respected team behind Max Bet is no stranger to the Bayliss Boatworks family, having previously entrusted us with the repower of their 66' Spencer. Posted on 4 Nov 2024
Bayliss Boatworks new construction updates
Big Deal Bayliss 75', Tarheel Bayliss 64', Mama Seata Bayliss 76' With the glassing phase complete on Big Deal's mezzanine, our exterior team has applied Awlfair, and sanding is currently under way to ensure a smooth, polished finish before the primer is applied. Posted on 3 Nov 2024
Bayliss Boatworks new construction updates
Max Bet will reside dockside until her christening later this month Max Bet will reside dockside until her christening later this month, with our mechanical team testing and proving all systems. Posted on 1 Oct 2024
Bayliss Boatworks new construction updates
DekIt team joined us this month to install nonskid foam decking in the engine room After a successful first sea trial earlier this month, our interior carpentry team jumped back onto Max Bet to assist with the installation of granite countertops in the lower staterooms. Posted on 2 Sep 2024
Bayliss Boatworks new construction updates
Max Bet 64', Big Deal Bayliss 75', Tarheel Bayliss 64' We are gearing up for Max Bet's first splash! Our mechanical and electrical teams have been busy installing the washer/dryer, sonar, and heat exchanger components, while Custom Marine Electronics has been working in the bridge. Posted on 3 Aug 2024
Bayliss Boatworks new construction updates
Max Bet 64', Big Deal Bayliss 75', Tarheel Bayliss 64' Next up for completion, Max Bet is drawing closer to the project's finish line! Our electrical team has been busy wiring the hardtop and the main panel. Posted on 5 Jul 2024
Bayliss Boatworks Sequentis Bayliss 60' update
The idea of the new project was a first for the company As a custom sportfishing boatbuilder, we take the requests of our owners and do our best to bring them to life. When collaborating with a long-time Bayliss Boatworks customer, the vision for a 60' walkaround was put on the drawing board. Posted on 4 Jul 2024