Jarrett Bay Boatworks - New construction updates
by Jarrett Bay Boatworks 30 Sep 2022 17:41 UTC

Hull 65, 64' Sportfisherman © Jarrett Bay Boatworks
Hull 65, 64' Sportfisherman
Furniture, cabinetry and systems installations are happening throughout the boat while the mezzanine compartments take shape. The bridge console and other structures are nearing completion and detail fairing work is happening on the hull. Mechanical and plumbing installations are also nearing completion.
View construction gallery
Hull 64, 68' Sportfisherman
Progress for the 68-footer includes the finishing of bilge areas and under-floor compartments in the down-forward section of the boat. Many equipment boxes and platforms have been fabricated in the engine and pump rooms and wire chases have been installed in the bulkheads between these spaces.
View construction gallery