Please select your home edition
Edition
Sail-World Asia
Sail-World Australia
Sail-World Canada
Sail-World Europe
Sail-World New Zealand
Sail-World United Kingdom
Sail-World USA
YachtsandYachting.com
Cruising Northern Hemisphere
Cruising Southern Hemisphere
Marine Business Europe
Marine Business North America
Marine Business Oceania
Powerboat.World Europe
Powerboat.World North America
Powerboat.World Oceania
FishingBoating.World Australia
FishingBoating.World New Zealand
FishingBoating.World USA
FishingBoating.World Asia
FishingBoating.World Canada
FishingBoating.World Europe
FishingBoating.World United Kingdom
NZ Boating World
Show Menu
HOME
PARIS 2024
AMERICA'S CUP
VENDÉE GLOBE
EDITORIAL
CATAMARANS
FAVOURITES
CLUBS
CLASSES
CALENDAR
FORUM
PHOTOS
VIDEOS
PARTNERS
CLASSIFIEDS
JOBS
SHOPPING
NEWSLETTERS
SUBMIT NEWS
CONTACT
STATS
Bayliss Boatworks new construction updates
by Bayliss Boatworks 3 May 2024 19:40 UTC
We are excited to debut the name of the latest 75 build at Bayliss Boatworks:
Big Deal
. She will be be welcomed into a well established fishing program, and after delivery will kick off her fishing expeditions along the East Coast and will eventually make the journey to Cabo and Costa Rica as well.
Last month on
Big Deal,
our exterior carpentry team glassed the bow deck, and worked on installing the toerail and cockpit AC. Our interior carpentry team has been busy putting mockups in place in the master stateroom. Next on the agenda, crews will install her structural cockpit decking and then the mezzanine buildout will begin.
CLICK TO READ MORE ABOUT BIG DEAL
Sequentis
hit the water for the first-time last month! Earlier in April, our team piled on for her maiden sea trial. Testing and proving was a success, and she has moved back into the make ready bay to receive a few finishing touches on the exterior. The bridge table and helm chair were both installed, while installation of cabinetry below deck remains ongoing. Josh Everett will be completing her transom artwork and we are closing in on the delivery date!
CLICK TO READ MORE ABOUT SEQUENTIS
Max Bet
saw many improvements last month. Our exterior carpentry team has been busy in the cockpit, installing the teak bullnose in the mezzanine, cockpit decking, and teak coverboards. Awlfair has been applied to the bridge flooring up in the flybridge, and in the interior, the dayhead cabinetry is now installed.
Max Bet
will be making moves soon and will head over to our paint facility in the next few weeks for topcoat.
CLICK TO READ MORE ABOUT MAX BET
The crews working on
Bayliss 64
had a productive month. With the forward fuel tank surround buildout complete, our mechanical team successfully installed the forward fuel tank. Meanwhile, our paint department continues sanding and priming the salon deck, and they recently finished painting the engine room. We are looking forward to
Bayliss 64s
engine installs scheduled for later this month!
CLICK TO READ MORE ABOUT BAYLISS 64'
Website
Facebook
Instagram
Copyright © 2024 Bayliss Boatworks All rights reserved.
www.baylissboatworks.com