Please select your home edition
Edition
Maritimo 2023 S-Series LEADERBOARD

Bayliss Boatworks new construction and boatyard updates

by Bayliss Boatworks 2 Jan 19:43 UTC
Happy New Year © Bayliss Boatworks
 
Boatyard Expansion February 2023
The Bayliss Boatyard expansion kicked off this past February, and work is winding down as the project timeline comes to a close. 10 new boat slips and 15 additional workspaces were added on the hard top. Nearly 1,000 linear feet of bulkhead, a 12,000 gallon fuel tank, and 25 100 amp shore power pedestals were also part of the new addition. We are looking forward to utlizing the new space in the year ahead!
Top left: April - Installing Boat Slips  ; Top right: August - Fuel Tank Install
Bottom: December - Boatyard Expansion 
 
2023 Build Highlights
  • Aft Fuel Tank Install
  • Engine and Salon Deck Installs
  • Cabin Install
  • Mezzanine, Bridge, and Interior Buildout
  • Teak Deck, Border, and Coverboard Installs
  • Exterior Sanded and Primed
CLICK TO READ MORE ABOUT SEQUENTIS
 
2023 Build Highlights
  • Forward Fuel Tank Install
  • Engine, Generator, Salon Deck Installs
  • Aft Fuel Tank and Seakeeper 18 Installs
  • Cabin Install
  • Mezzanine, Interior, Flybridge Buildouts
  • Exterior Sanded and Primed
CLICK TO READ MORE ABOUT MAX BET
 
2023 Build Highlights
  • Hull Jig Assembled
  • Whiskey Plank
  • Bulkhead Install
  • Machine Tunnel and Engine Room Buildouts
  • Forward Fuel Tank Install
  • Engines, Generators, Seakeeper 18, and Salon Deck Installs
CLICK TO READ MORE ABOUT BAYLISS 75'
 
2023 Build Highlights
  • Project Start: August 2023
  • Hull Jig Assembled
  • Whiskey Plank
  • Hull Glassed and Sanded
CLICK TO READ MORE ABOUT BAYLISS 64'
 
 
 
Website
Website
Facebook
Facebook
Instagram
Instagram

Copyright © 2024 Bayliss Boatworks All rights reserved.
www.baylissboatworks.com 

Related Articles

Bayliss Boatworks new construction updates
Max Bet 64', Big Deal Bayliss 75', Tarheel Bayliss 64' Next up for completion, Max Bet is drawing closer to the project's finish line! Our electrical team has been busy wiring the hardtop and the main panel. Posted on 5 Jul
Bayliss Boatworks Sequentis Bayliss 60' update
The idea of the new project was a first for the company As a custom sportfishing boatbuilder, we take the requests of our owners and do our best to bring them to life. When collaborating with a long-time Bayliss Boatworks customer, the vision for a 60' walkaround was put on the drawing board. Posted on 4 Jul
Bayliss Boatworks new construction updates
The final touches are wrapping up on our first walkaround build! The final touches are wrapping up on our first walkaround build! Posted on 2 Jun
Bayliss Boatworks new construction updates
The latest 75' build at Bayliss Boatworks: Big Deal We are excited to debut the name of the latest 75' build at Bayliss Boatworks: Big Deal. Posted on 3 May
Bayliss Boatworks new construction updates
Sequentis is getting closer to hitting the water! Earlier in March, our mechanical team with the help of Palm Beach Towers installed her custom hardtop. Posted on 2 Apr
Bayliss Boatworks new construction updates
Our first walkaround build is really coming together! Our first walkaround build is really coming together! With full paint complete, Sequentis returned to the main shop's make-ready bay for our exterior carpentry team to prep for tower installation. Posted on 2 Mar
Bayliss Boatworks new construction updates
Our teams had a productive month on Sequentis January was a heavy month of boat moves for our mechanical team! After being prepped for final paint, Sequentis was shifted over to our paint facility to have her top coat sprayed. Posted on 3 Feb
Bayliss Boatworks new construction updates
Progress on Sequentis is moving right along! Progress on Sequentis is moving right along! Both the mezzanine buildout and cockpit deck installation are now complete. Posted on 2 Dec 2023
Bayliss Boatworks new construction updates
Steady progress is happening on Sequentis Steady progress is happening on Sequentis. Super Build was applied to the bridge and mezzanine, and crews are now sanding these areas in preparation for primer. Posted on 2 Nov 2023
Bayliss Boatworks new construction updates
Our teams had a productive month on Sequentis Our teams had a productive month on Sequentis. With the teak deck installed on the walkaround, our exterior construction crew is continuing progress on the bridge dash, storage compartments, and mezzanine lids. Posted on 2 Oct 2023
Maritimo 2023 S600 FOOTER