Bayliss Boatworks new construction updates

by Bayliss Boatworks 1 Jul 2023 23:44 UTC
 
June was a productive month for our exterior carpentry team on the walkaround build. On the bow, the anchor locker hatch has been installed. Progress on the fish box buildout continues in the cockpit, and coverboards are being installed as well. In the lower accommodations on Sequentis, mockups are being set in place by our interior carpentry crew! 
CLICK TO READ MORE ABOUT SEQUENTIS
 
Steady progress is being made on the 64' Max Bet. The anchor locker buildout is progressing on the bow, and the hatch is being fabricated. Our exterior carpentry team has been busy glassing the salon and lazarrette, and our interior carpentry team is working on installing mockups throughout the lower accommodations. Next month, crews will focus on glassing the bow deck and beginning the cockpit deck buildout.  
CLICK TO READ MORE ABOUT MAX BET
 
Since her recent flip, our team has been working hard over in the hull shop. Our paint crew continues to fair and sand the hull on Bayliss 75', and our hull carpentry team recently installed the bulkheads for the engine room, pump room, and lazarette. The bow thruster tube was recently installed and the machine tunnel buildout is currently in the works.
 
CLICK TO READ MORE ABOUT BAYLISS 75'
 
 
 
Website
Website
Facebook
Facebook
Instagram
Instagram

Copyright © 2023 Bayliss Boatworks All rights reserved.
www.baylissboatworks.com 

Related Articles

Bayliss Boatworks new construction updates
Big news from Big Deal! Big news from Big Deal! Late last month, she successfully completed her first sea trial—a major milestone as she moves closer to delivery. Posted on 2 May
Bayliss Boatworks new construction updates
Big Deal is reaching significant milestones Big Deal is reaching significant milestones, starting with a major exterior update. Posted on 2 Apr
Bayliss Boatworks new construction updates
Big Deal was moved to the paint facility early last month to begin the full paint process Following our paint team's meticulous sanding of the hull, Big Deal was moved to our paint facility early last month to begin the full paint process. Posted on 2 Mar
Bayliss Boatworks new construction updates
Big Deal ready for its scheduled move to the paint bay in early March With the bridge console faired, our paint team is steadily progressing with priming and sanding, getting Big Deal ready for its scheduled move to the paint bay in early March. Posted on 1 Feb
Bayliss Boatworks new construction updates
Progress on Big Deal continues as the cockpit and mezzanine have been outfitted Progress on Big Deal continues as the cockpit and mezzanine, now fully primed, have been outfitted with a teak bullnose, teak decking, and teak mezzanine lids by our exterior carpentry team. Posted on 2 Jan
Bayliss Boatworks new construction updates
The paint team has started applying primer to the mezzanine on Big Deal With the mezzanine buildout complete on Big Deal, the paint team has started applying primer to the area. Posted on 3 Dec 2024
Max Bet Bayliss 64' on the water
The culmination of over 60,000 man-hours of dedicated craftsmanship The well-respected team behind Max Bet is no stranger to the Bayliss Boatworks family, having previously entrusted us with the repower of their 66' Spencer. Posted on 4 Nov 2024
Bayliss Boatworks new construction updates
Big Deal Bayliss 75', Tarheel Bayliss 64', Mama Seata Bayliss 76' With the glassing phase complete on Big Deal's mezzanine, our exterior team has applied Awlfair, and sanding is currently under way to ensure a smooth, polished finish before the primer is applied. Posted on 3 Nov 2024
Bayliss Boatworks new construction updates
Max Bet will reside dockside until her christening later this month Max Bet will reside dockside until her christening later this month, with our mechanical team testing and proving all systems. Posted on 1 Oct 2024
Bayliss Boatworks new construction updates
DekIt team joined us this month to install nonskid foam decking in the engine room After a successful first sea trial earlier this month, our interior carpentry team jumped back onto Max Bet to assist with the installation of granite countertops in the lower staterooms. Posted on 2 Sep 2024