Please select your home edition
Edition
Sea Sure 2020 - SHOCK-WBV - LEADERBOARD

Bayliss Boatworks new construction update - Bayliss 75'

by Bayliss Boatworks 2 Apr 14:22 UTC

With the finish line in sight, our crews stayed busy on Bayliss 75' last month.

The transom is prepped for the transom artwork to be done by Everett Nautical, and electronics from Custom Marine Electronics are now in place in the flybridge.

The interior is beginning to look more complete with the installation of faucets, shower doors, headliner, and the washer and dryer. Cabinetry items are also being installed by our interior carpentry department in the lower accommodations.

After a productive month, big plans are lined up for Bayliss 75'. Next week she will hit the water for her first sea trial!

Read more about Bayliss 75' here...

Related Articles

Bayliss 75' new construction update
April was an eventful month for Wave Paver She will be the second Bayliss custom yacht to join the Wave Paver fishing program, and we are excited to see all this team accomplishes in their future endeavors. Posted on 6 May
Bayliss 60' new construction update
Major changes have been made on Sequentis this past month On the hull, Awlfair has been applied and the bottom and sides were sanded. Our paint department painted her hull sides, and Sequentis was then moved to our west campus. Posted on 3 May
Bayliss 68' Overtime new construction update
Progress continues in the cockpit The teak border, cockpit deck, and coverboards were all installed in April. Our paint crew has also been hard at work with the primiing of the mezzanine now complete. Posted on 2 May
Bayliss 60' Sequentis new construction update
Our hull carpentry crew secured the final hull plank. Sequentis checked off a milestone in early March with the infamous whiskey plank. Our hull carpentry crew secured the final hull plank, and now all the layers of planking are complete! Posted on 8 Apr
Bayliss 68' Overtime new construction update
The first hints of walnut have made their way into the build. The first hints of walnut have made their way into the build with the salon veneers and master stateroom hanging lockers installed. Posted on 5 Apr
Bayliss 60' Sequentis new construction update
The hull carpentry department has been making major headway In early February, the stringers, chine, and sheer log were all laminated in place and shaped. With the solid foundation created, our team completed planking the first, second and third layers of the hull bottom. Posted on 6 Mar
Bayliss 68' Overtime new construction update
Progress continues in the cockpit and mezzanine Progress continues in the cockpit and mezzanine on Overtime. Our exterior carpentry crew glassed the cockpit structural decking and is busy adding insulation to the lower boxes on the mezzanine. Posted on 4 Mar
Bayliss 75' new construction update
All the details are coming together All the details are coming together on Bayliss 75'. Our Interior carpentry crew has been busy installing cabinetry, wainscoting in the companionway, and the walnut flooring borders. Posted on 2 Mar
Full paint officially complete on Bayliss 75'
And the successful installation of the hard top and tower Bayliss 75' had an eventful month! With full paint officially complete, Palm Beach Towers, with the help of our mechanical crew, successfully installed the hard top and tower. Posted on 5 Feb
Bayliss 60' Sequentis construction update
Work begins on the custom sportfishing walkaround with 360 degrees of fishability In the first week of January, Bayliss Boatworks began construction on their newest project: Sequentis. The 60' custom sportfishing walkaround will have 360 degrees of fishability. Posted on 4 Feb
38 South - Marlin 795 - FOOTER - Sept2021Marina Exchange FOOTER 1Sea Sure 2020 - SHOCK-WBV - FOOTER