Bayliss Boatworks new construction updates - Bayliss 75' and Bayliss 67' Overtime

by Bayliss Boatworks 4 Oct 2021 13:57 UTC
Bayliss 75' © Bayliss Boatworks

Bayliss 75'

Work on Bayliss 75' moved along steadily this past month, with our mechanical team installing the fuel fill lines, chillers, generator controls, and low-pressure water maker pumps and strainers.

The installation of upper mezzanine storage and teak coaming has kept our exterior construction department busy.

In the interior, our cabinetry crew has installed the salon sofa base and additional mockups to the tackle room. Various cabinetry items are in finish, and hints of walnut are beginning to appear on the build. Hull 27 is the first Bayliss build to feature walnut veneer.

Read more about Bayliss 75' here...

Bayliss 67' Overtime

Overtime's silhouette had a major transformation this past month. After our carpentry crew finished the installation of the bow deck, her cabin was installed. Progress continues with the buildout in the gyro and fuel tank surround, which will soon be sanded and primed by our paint department in preparation for top coat.

Priming is under way in the lazarette and our mechanical department has installed the livewell plugs. The salon deck has been glassed in place and we are looking forward to installing the salon bulkhead on Overtime next!

Read more about Overtime here...

Related Articles

Bayliss Boatworks new construction updates
Sequentis is getting closer to hitting the water! Earlier in March, our mechanical team with the help of Palm Beach Towers installed her custom hardtop. Posted on 2 Apr
Bayliss Boatworks new construction updates
Our first walkaround build is really coming together! Our first walkaround build is really coming together! With full paint complete, Sequentis returned to the main shop's make-ready bay for our exterior carpentry team to prep for tower installation. Posted on 2 Mar
Bayliss Boatworks new construction updates
Our teams had a productive month on Sequentis January was a heavy month of boat moves for our mechanical team! After being prepped for final paint, Sequentis was shifted over to our paint facility to have her top coat sprayed. Posted on 3 Feb
Bayliss Boatworks new construction updates
Looking forward to utlizing the new boatyard space in the year ahead The Bayliss Boatyard expansion kicked off this past February, and work is winding down as the project timeline comes to a close. Posted on 2 Jan
Bayliss Boatworks new construction updates
Progress on Sequentis is moving right along! Progress on Sequentis is moving right along! Both the mezzanine buildout and cockpit deck installation are now complete. Posted on 2 Dec 2023
Bayliss Boatworks new construction updates
Steady progress is happening on Sequentis Steady progress is happening on Sequentis. Super Build was applied to the bridge and mezzanine, and crews are now sanding these areas in preparation for primer. Posted on 2 Nov 2023
Bayliss Boatworks new construction updates
Our teams had a productive month on Sequentis Our teams had a productive month on Sequentis. With the teak deck installed on the walkaround, our exterior construction crew is continuing progress on the bridge dash, storage compartments, and mezzanine lids. Posted on 2 Oct 2023
Bayliss Boatworks new construction updates
Hull jig for our latest project: Bayliss 64' assembled This past month, we assembled the hull jig for our latest project: Bayliss 64'. Posted on 2 Sep 2023
Bayliss Boatworks new construction updates
July work on Sequentis 60', Max Bet 64' and Bayliss 75' The mezzanine and bridge buildout on Sequentis kept our exterior carpentry crew busy this past month. Storage and seating can be seen on the bridge now, and fabrication on the forward bridge storage compartments has begun. Posted on 2 Aug 2023
Bayliss Boatworks new construction updates
June was a productive month for our exterior carpentry team June was a productive month for our exterior carpentry team on the walkaround build. Posted on 1 Jul 2023