Bayliss Boatworks construction update: Bayliss 72' Old Reliable

by Bayliss Boatworks 4 Jul 2021 17:29 UTC
Bayliss 72' Old Reliable © Bayliss Boatworks

Old Reliable hit the water for the first time this past month. After a successful sea trial, she was hauled out to receive finishing touches to the exterior.

With her boot-stripe, bottom paint and transom artwork applied, Old Reliable took a spin in the creek before moving into her slip for the duration of her build.

Superior Marble installed the granite countertops in the galley and day head, and our Interior Carpentry Crew has been adding the finishing touches in the galley and staterooms. Headliners and wall panels are getting installed, and the dinette and sofa are making their move onto the boat this week.

We are looking forward to Old Reliable's Christening later this summer!

Read more about Old Reliable here...

Related Articles

Bayliss Boatworks new construction updates
Bayliss 75' has made her move over to the paint bay With sanding complete, Bayliss 75' has made her move over to the paint bay for final paint! Our interior department has installed the salon door, as well as the majority of cabinetry items in the galley. Posted on 2 Jan
Bayliss 75 & Bayliss 67 Overtime build highlights
From empty hull at the beginning of the year to now nearing the final stages Bayliss 75' went from an empty hull at the beginning of the year to now nearing the final stages of her build. Bayliss 67' started the year upside down and has been flipped and filled with major mechanical components. Posted on 2 Dec 2021
Bayliss 75' and Bayliss 67' Overtime updates
Electrical department has begun wire runs in the Bayliss 75' console The flybridge on Bayliss 75' saw some major enhancements this past month. The teak helm pod and teak rod locker cap have been installed and finish has been applied. Posted on 2 Nov 2021
Bayliss 75' and Bayliss 67' Overtime updates
Work has moved along steadily this past month Work on Bayliss 75' moved along steadily this past month, with our mechanical team installing the fuel fill lines, chillers, generator controls, and low-pressure water maker pumps and strainers. Posted on 4 Oct 2021
Bayliss 75' and Bayliss 67' Overtime updates
Next in line for completion, Bayliss 75' saw many detail changes over the last month Next in line for completion, Bayliss 75' saw many detail changes over the last month. Our interior cabinetry team has been busy installing and applying finish to the salon veneers, bringing a new look to the interior of the hull. Posted on 4 Sep 2021
Bayliss Boatworks delivers Old Reliable 72'
Nick Smith is the proud owner of the custom sport fishing yacht Bayliss Boatworks is proud to announce the delivery of Old Reliable, a 72' custom sport fishing yacht. Her christening took place on August 6th, in a gathering with friends and family. Posted on 2 Sep 2021
Tournament wins for Bayliss yacht teams
Tarheel (Bayliss 62') wins at home in Dare County Boat Builders Tournament Congratulations to the guys on Tarheel for receiving first place in the Dare County Boat Builders Tournament. With two consistent days of fishing, the crew topped the leaderboards in billfish releases with five white marlin and one blue marlin. Posted on 4 Aug 2021
Bayliss Boatworks new construction updates
Old Reliable (Hull 5) paid a visit to Old Reliable (Hull 25) to see how things were going Old Reliable (Hull 5) paid a visit to Old Reliable (Hull 25), to see how things were going in the final stages of her build. With a few successful fishing trips in the books, she is almost ready for christening on August 6th. Posted on 3 Aug 2021
Bayliss 75' construction update
The Paint Department has been working on sanding the flybridge console Down below, the cockpit structural decking was sanded and glassed, and the fishbox was also installed and glassed. Our Exterior Carpentry Crew has begun construction on the washboards for Hull 27, which will be put in place in the coming weeks. Posted on 6 Jul 2021
Bayliss 67' Overtime construction update
The crew now has the pump shelf in paint and the generator shelves are in glass as well In June, Overtime saw improvements to the interior of the hull. Our paint department has been busy fairing, sanding and adteching the interior pump shelf. Posted on 5 Jul 2021