Bayliss Boatworks construction update: Bayliss 72' Old Reliable

by Bayliss Boatworks 2 May 10:27 UTC

Progress on Old Reliable (Bayliss 72') has been coming along steadily, and she is starting to take shape with her recently installed tower and hardtop.

Our paint department was hard at work this month getting ready for top coat, which is now complete. Izzy Teak also put the finishing touches on the faux teak toe rail.

The project focus over the next few weeks will be in the salon, galley and lower staterooms, with the installation of the dinette, salon TV cabinet, and cabinetry in the Master and Captain's staterooms.

Pretty soon, she will be making her first splash in preparation for receiving her boot-stripe and transom artwork!

Read more about Old Reliable here...

Related Articles

Bayliss 67' Overtime construction update
Forward fuel tank and fuel tank deck installed Overtime (Bayliss 67') had a few installs of her own this past month. The forward fuel tank was installed and the fuel tank deck was installed shortly thereafter. Posted on 7 Jun
Bayliss 72' Old Reliable construction update
She is nearing the final stages of production In the flybridge, our Electrical Department with the help of Custom Marine Electronics installed multiple marine-electronic items. They also installed the electrical panels. Posted on 5 Jun
Bayliss 75' construction update
Our Paint Department has been busy with improvements to the exterior Bayliss 75' peeked out from the construction bay this past month, for the install of her aft fuel tank. The foam insulation was installed shortly after, and we are preparing for the installation of the cockpit decking next. Posted on 3 Jun
Bayliss 67' Overtime construction update
The machine tunnel build-out continues with glassing of the forward fuel tank surround This past month, Overtime (Bayliss 67') had her hull exterior sanded and primed. Down in the engine room, construction of the generator shelves, pump shelf, battery boxes, and bilge is well under way. Posted on 6 May
Bayliss 75' construction update
The exterior carpentry department has been busy glassing the cabin to the hull Advancements to the exterior of Bayliss 75' continued this past month. Now that the cabin and bow deck have been installed, she is ready for lower level paint to begin. Posted on 3 May
Bayliss 67' Overtime construction update
Work continues inside the hull after being flipped right side up Work continues inside the hull of Overtime (Bayliss 67') after being flipped right side up early in the month. Glassing was completed on the interior of the hull bottom before her main structural and engine bulkheads were installed. Posted on 7 Apr
Bayliss 75' construction update
Looking a lot different this month with the addition of her cabin Our mechanical crew also installed her aft gyro, the last of her main mechanical components, before returning back to the construction bay. Posted on 5 Apr
Bayliss 72' Old Reliable construction update
Old Reliable getting more interior and exterior details finalized Old Reliable (Bayliss 72') is on the move from the make-ready bay to the paint bay after a busy month, getting more interior and exterior details finalized. Posted on 3 Apr