New construction updates - Bayliss 75'

by Bayliss Boatworks 3 Mar 2019 03:52 UTC
Bayliss 75' © Bayliss Boatworks

The month of February made things real for Bayliss 75' as this build nears completion. One of the biggest benchmarks was checked off in early February- her first sea trial.

After sea trials, Bayliss 75' was slid back inside the shop for her final paintwork while our cabinetry team continued work on her interior. She re-emerged last week with a striking red and gold water line and transom lettering. Our paint crew will now apply nearly a dozen coats of clear coat to the transom to seal the surface and accentuate the shine.

This close to the finish line, we're focusing on the hundreds of details that will make Bayliss 75' whole. Electronics, custom rod storage, soft goods, carpet, and much more are on our punch list as we get closer to her final launch date.

Look for delivery of Bayliss 75' in early spring of 2019

This build will be part of a two-boat program (as the larger of the owner's two boats), and the owner's second Bayliss hull.

Specifications:

  • Start Date: February 2017
  • Length: 75'
  • Beam: 20' 8"
  • Draft: 5' 10"
  • Power: (2) MTU M96L 16V @ 2,600 hp each
  • Gyro: Seakeeper 26
  • Genset: (2) 30kw Northern Lights
  • Fuel Capacity: 2,650 gallons
  • Water Capacity: 450 gallons
  • Water Maker: (2) 1,200 gal. per day and dockside treatment system
  • Holding Tank: 200 gal.
  • Interior Layout: 4 staterooms, 3.5 heads, Pantry
  • Cockpit Layout: Mezzanine Style Cockpit with Teak Aft Bulkhead
  • Bridge Layout: Center Console, Two Freezers, Two helm chairs
Read more about the Bayliss 75' here.

Related Articles

Bayliss Boatworks new construction updates
Big news from Big Deal! Big news from Big Deal! Late last month, she successfully completed her first sea trial—a major milestone as she moves closer to delivery. Posted on 2 May
Bayliss Boatworks new construction updates
Big Deal is reaching significant milestones Big Deal is reaching significant milestones, starting with a major exterior update. Posted on 2 Apr
Bayliss Boatworks new construction updates
Big Deal was moved to the paint facility early last month to begin the full paint process Following our paint team's meticulous sanding of the hull, Big Deal was moved to our paint facility early last month to begin the full paint process. Posted on 2 Mar
Bayliss Boatworks new construction updates
Big Deal ready for its scheduled move to the paint bay in early March With the bridge console faired, our paint team is steadily progressing with priming and sanding, getting Big Deal ready for its scheduled move to the paint bay in early March. Posted on 1 Feb
Bayliss Boatworks new construction updates
Progress on Big Deal continues as the cockpit and mezzanine have been outfitted Progress on Big Deal continues as the cockpit and mezzanine, now fully primed, have been outfitted with a teak bullnose, teak decking, and teak mezzanine lids by our exterior carpentry team. Posted on 2 Jan
Bayliss Boatworks new construction updates
The paint team has started applying primer to the mezzanine on Big Deal With the mezzanine buildout complete on Big Deal, the paint team has started applying primer to the area. Posted on 3 Dec 2024
Max Bet Bayliss 64' on the water
The culmination of over 60,000 man-hours of dedicated craftsmanship The well-respected team behind Max Bet is no stranger to the Bayliss Boatworks family, having previously entrusted us with the repower of their 66' Spencer. Posted on 4 Nov 2024
Bayliss Boatworks new construction updates
Big Deal Bayliss 75', Tarheel Bayliss 64', Mama Seata Bayliss 76' With the glassing phase complete on Big Deal's mezzanine, our exterior team has applied Awlfair, and sanding is currently under way to ensure a smooth, polished finish before the primer is applied. Posted on 3 Nov 2024
Bayliss Boatworks new construction updates
Max Bet will reside dockside until her christening later this month Max Bet will reside dockside until her christening later this month, with our mechanical team testing and proving all systems. Posted on 1 Oct 2024
Bayliss Boatworks new construction updates
DekIt team joined us this month to install nonskid foam decking in the engine room After a successful first sea trial earlier this month, our interior carpentry team jumped back onto Max Bet to assist with the installation of granite countertops in the lower staterooms. Posted on 2 Sep 2024
Maritimo 2023 M600 FOOTERPalm Beach Motor Yachts